| Activity | A | B | C | D | E | F | G | H |
|---|---|---|---|---|---|---|---|---|
| Duration | 4 | 10 | 5 | 15 | 12 | 4 | 8 | 7 |
| Early Start | 0 | 0 | 4 | 10 | 10 | 25 | 22 | 30 |
| Early Finish | 4 | 10 | 9 | 25 | 22 | 29 | 30 | 37 |
| Late Start | 2 | 0 | 6 | 11 | 10 | 26 | 22 | 30 |
| Late Finish | 6 | 10 | 11 | 26 | 22 | 30 | 30 | 37 |
| Total Slack | 2 | 0 | 2 | 1 | 0 | 1 | 0 | 0 |
The critical path is B-E-G-H with duration: 37
To Top
| Activity | Optimistic | Most Likely | Pesimistic | Average |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Path Total Expected Time
A-C 8+6
= 14.00
A-D-E 8+4+7 = 19.00
B-E 7.83
+ 7 = 14.83
The critical path is A-D-E since it is the longest path. Expected project duration is 19.00 (sum of the
expected durations of critical activities)
z = (T - TE)/ standard
deviationof project duration = (21 - 19) / (2.440.5)
= 1.28
Assuming normal distribution applies, the probability that the
projectcan be completed within 21 days is about 90%.

| Activity | Start | A | B | C | D | E | F | Finish |
| Duration | 0 | 5 | 3 | 2 | 5 | 4 | 7 | 0 |
| ES | 0 | 0 | 0 | 5 | 3 | 8 | 8 | 15 |
| EF | 0 | 5 | 3 | 7 | 8 | 12 | 15 | 15 |
| LS | 0 | 4 | 0 | 9 | 3 | 11 | 8 | 15 |
| EF | 0 | 9 | 3 | 11 | 8 | 15 | 15 | 15 |
| Slack | 0 | 4 | 0 | 4 | 0 | 3 | 0 | 0 |

Critical path, using normal durations, is A-D-G with a
duration of 29. Direct cost of this schedule is $13,050.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Note: Since the project is rather simple we could have calculated
the critical path by enumerating all the paths to select the longest one
as the critical path.
A-D-G 29
A-E-H 26
B-F-H 23
C-I 22
Clearly, the path A-D-G must be reduced by four time units, A-E-H one
to bring all the paths to within 25 time units.
Cost analysis:
| Activity | Crash Cost/Day | Maximum Crash |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Activity |
Critical Path |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
A-E-H |
|
|
|